The project owner is the world's largest steel maker and is expanding its plant at Hazira, Gujarat from 9 MTPA to 15 MTPA. The L1 project developer for expansion of the steel plant is part of a salt-to-sky conglomerate and is one of India's largest EPC infrastructure companies. Moglix has provided 5000 MT fabrication, raw materials and painting for the project.

Business Challenges

  • >Need for one-stop solution
  • >QAP for procurement
  • >Fabrication at EPC approved facility only
  • >+/- 10% margin error allowed

5000 MT of Fabricated Structures Delivered in 12 Months

Solution

Explore how Moglix is providing capex project procurement solutions for expansion of a steel plant in Hazira